What is the minimum period of curing?
Share
Lost your password? Please enter your email address. You will receive a link and will create a new password via email.
Please briefly explain why you feel this question should be reported.
Please briefly explain why you feel this answer should be reported.
Please briefly explain why you feel this user should be reported.
For most concrete structures, the curing period at temperatures above 5º C (40º F) should be a minimum of 7 days or until 70% of the specified compressive or flexural strength is attained. The period can be reduced to 3 days if high early strength concrete is used and the temperature is above 10º CRead more
For most concrete structures, the curing period at temperatures above 5º C (40º F) should be a minimum of 7 days or until 70% of the specified compressive or flexural strength is attained. The period can be reduced to 3 days if high early strength concrete is used and the temperature is above 10º C (50º F).
See less